Dependencies and the timeline

Project planning adds structure to a tasks database: tasks can have sub-items, a task can wait for other tasks, and tasks with a start and end date appear on a timeline. When dates no longer fit the order of the work, Venolio can reschedule the waiting tasks for you.

Open it from the database’s More database actions menu → Project planning (see Sprints).

The Tasks view

The Tasks view lists the tasks with the columns Task, Sprint, Dates and Blocked by. Tasks with sub-items have an arrow to show or hide them. Click a title to open the task.

Add a sub-item

  1. Click + next to a task (Add sub-item).
  2. Type a Title and click Create sub-item.

The sub-item is a new record in the same database, under that task. To move a task under another one, edit it and choose a Parent task (No parent to make it top level).

Make a task wait for another

  1. Click the pencil next to the task that has to wait.
  2. Under Blocked by, choose the task it waits for in Add a task it waits for…. It is saved at once.
  3. To remove one, click Remove dependency next to it.
  4. In the same dialog you can set Start and End dates; click Save task.

While a task it waits for is not done, the task shows the warning Waiting on another task in the project pulse and is listed under Blocked in My work.

Rules:

  • Sub-items and dependencies stay within one database.
  • A task cannot wait for itself, directly or through other tasks, and cannot be its own parent. Venolio refuses a change that would make a loop.
  • Sub-items can be nested up to 63 levels.
  • A date range needs both dates and spans at most 366 days.

The timeline

The Timeline view draws every task that has a start and end date as a bar, with lines for the dependencies between them.

  • Drag a bar to move the task; its length stays the same.
  • Drag the left or right edge of a bar to change its start or end.
  • With the keyboard, focus a bar and press Enter to edit its dates.

Each change is saved when you let go. Tasks without dates are not shown; add dates in the Tasks view.

Reschedule dependencies

When a task starts before the tasks it waits for are finished, reschedule:

  1. Click Reschedule dependencies.
  2. Review dependency schedule lists the tasks that would move and their new dates. Each moves to start the day after the last task it waits for ends, keeping its duration. Other tasks stay where they are.
  3. Click Apply to make the changes, or cancel.

If nothing needs to move, the preview says so. If any of the listed tasks changed after the preview, applying is refused; reschedule again to get a fresh preview. You need edit access to every task that moves.

Who can do what

  • Everyone who can open the database sees the plan. A task you cannot open appears as Unavailable in the Blocked by column.
  • Editing tasks, dates and dependencies needs edit access to the database and to the task.

Limits

Limit Value
Planned tasks per database 5,000
Dependencies per database 10,000
Sub-item depth 63 levels
Date range of a task 366 days

Dependencies between pages

Task dependencies say which task waits for which. Separately, any page can record that it uses another page, for example a service that calls another service. You enter these in the Dependencies section of a page’s info, and they are drawn on the dependency map. See Search and knowledge.

When repositories are connected, Venolio can find such dependencies in code and offer them under Suggested from code, in the page’s Dependencies section and on the dependency map. Click Accept to add one as a dependency, or Dismiss to hide it. Nothing is added until someone accepts it.